[单选] 施工过程中,由于甲承包商的分包商施工延误,导致乙承包商不能按进度计划施工,造成费用增加和工期延误,乙承包商应向()提出索赔意向通知。

A . 发包人
B . 工程师
C . 甲承包商
D . 甲承包商的分包商

You are designing a Windows Azure web application.  All users authenticate by using their Active Directory Domain Services (AD DS) credentials.  You need to recommend an approach for enabling single sign-on for domain-authenticated users.   Which two actions should you recommend?()  Use Forms authenticationto generate claims.。  Use Active Directory Federation Services (AD FS) to generate claims.。  Use SqlMembershipProvider in the web application.。  Use Windows Identity Foundation in the web application.。 You need to design a patch management strategy for Southbridge Video. Your solution must meet business requirements. What should you do?() Configure all client computers to use Automatic Updates to obtain security patches from the Windows Update Web site. Test and install all patches。 Configure a batch file to download security patches daily. Distribute the security patches by using a.zap file and the Default Domain Policy Group Policy object (GPO)。 Deploy a Software Update Services (SUS) server. Test all security patches and then approve them. Configure all client computers to automatically obtain updates from the server。 Configure a batch file to download security patches daily. Manually install the security patches on all computer。 互联网的应用范围有()。 A.电子商务 。 B.媒体 。 C.社交 。 D.娱乐。 焦炉煤气一氧化碳含量是()%,所以极具危险性。 6~9。 27~31。 50~65。 60~67。 共济失调 施工过程中,由于甲承包商的分包商施工延误,导致乙承包商不能按进度计划施工,造成费用增加和工期延误,乙承包商应向()提出索赔意向通知。
参考答案:

  参考解析

本题暂无解析

在线 客服