问题:

[单选] 为实现进度目标,不但应进行进度控制,还应注意分析影响工程进度的风险,并在分析的基础上采取风险管理措施,以减少进度失控的风险量,这是施工方进度控制的()。

A . 经济措施
B . 组织措施
C . 管理措施
D . 技术措施

项目信息管理的目的旨在通过有效地项目信息()为项目建设的增值服务。 A.存档和处理 。 B.处理和交流 。 C.传输的组织和控制 。 D.收集和存储。 Your network consists of an Active Directory forest that contains two domains. All servers run  Windows Server 2008 R2. All domain controllers are configured as DNS servers.     You have a standard primary zone for dev.contoso.com that is stored on a member server.     You need to ensure that all domain controllers can resolve names from the dev.contoso.com  zone.     What should you do() On the member server, create a stub zone.。 On the member server, create a NS record for each domain controller.。 On one domain controller, create a conditional forwarder. Configure the conditional forwarder to replicate to all DNS。 On one domain controller, create conditionals forwarder. Configure the conditional forwarder to replicate to all DNS。 淘汰值是将样本内观察到的杂株与标准规定值进行比较,作出有风险接受或淘汰种子田决定的数值,它与哪个因素密切相关?() 作物种类。 种子质量。 品种类型。 样本大小。 药物与血浆蛋白结合() 是永久性的。 对药物的主动转运有影响。 是可逆的。 加速药物在体内的分布。 促进药物排泄。 你正在创建一个组合 Web 控件。你应该如何增加子控件?() 实现INaming Container接口.。 重载Create Child Controls方法,并创建子控件。。 重载Controls属性,并调用Ensure Child Controls方法.。 增加控件到.ascx文件.。 为实现进度目标,不但应进行进度控制,还应注意分析影响工程进度的风险,并在分析的基础上采取风险管理措施,以减少进度失控的风险量,这是施工方进度控制的()。
参考答案:

  参考解析

为实现进度目标,不但应进行进度控制,还应注意分析影响工程进度的风险,并在分析的基础上采取风险管理措施,以减少进度失控的风险量。这是施工方进度控制的管理措施。

在线 客服